A schedule impact analysis is how you show a GC that a delay or change cost you time, and exactly how much. For a masonry, electrical, drywall or HVAC sub, the method matters less than the paper behind it: dated daily reports, photos, RFI and submittal logs, and a notice sent on time. The analysis is only as good as those records, and we built Subascent so a sub's field and office records land in one place.
TL;DR
- A schedule impact analysis quantifies how a delay or change moves the project completion date, then assigns that time to whoever caused it.
- The standard method is a time impact analysis (TIA): insert the delay as a small set of activities into the last accepted schedule update, recalculate, and compare completion dates.
- Float eats delay first. A 15-day delay on a path with 4 days of float is an 11-day claim, not 15.
- Weather days usually count only above a contract baseline, and only with daily logs, photos and nearby weather station data.
- Your foremen's daily reports decide whether the claim survives review.
Table of Contents
- What a schedule impact analysis actually measures
- Time impact analysis step by step
- Float comes first: a worked example
- Delay impact analysis with other methods
- What a trade sub needs in the file
- Weather delay days
- A repeatable routine for your office
- How Subascent fits
- Our view
- FAQ
- Sources
What a schedule impact analysis actually measures
John Hildreth's schedule impact analysis guide describes it as quantifying and apportioning the effect of a delay or change on the schedule. Two words matter.
Delay: an event that keeps work from finishing inside the contract period. Change: work that departs from the original contract and adds time. Before you claim time for a change, make sure it really is one and not something your original scope already covered.
The analysis starts with three pictures of the job: the as-planned baseline, the as-built record of what has been done, and the remaining schedule after the event. The gap between the planned and projected completion dates is the total impact. Then comes the part subs care about: who owns that time. Hildreth warns against granting the full length of a delay as the extension. The critical path decides what is actually owed.
Who needs this
If you are a trade sub, you rarely write the CPM schedule. The GC or its scheduler owns it. But you are the one who loses crew days when a shop drawing comes back late, a slab is not ready, or the weather shuts down the block wall. You supply the facts. The GC's scheduler usually runs the model, so your job is to hand over a clean, dated, specific record.
Time impact analysis step by step
A time impact analysis (TIA) is the most common form. The American Bar Association's 2022 article on construction scheduling explains that it inserts the event as a fragmentary network, or fragnet, into the CPM schedule. A fragnet is a short chain of activities and links that represents the delay. Here is how it runs, with where subs go wrong at each step.
- Send notice first. Most subcontracts set a short window to notify the GC of a potential time impact. TxDOT's job aid starts the whole process from a notice of potential time impact. Miss the window and the best analysis in the world may not matter. Check your subcontract for the exact deadline.
- Pick the right unimpacted schedule. Ron Winter's procedure uses the last accepted update before the delay, or the baseline if the delay began before the first update. The ABA article says the update immediately before the event is typically appropriate. Where subs go wrong: pointing at a schedule the GC never accepted.
- Build the fragnet small. Winter recommends as few activities and relationships as possible, and the owner should review and approve the fragnet before the analysis proceeds. AACE 52R-06 says the same: reduce it to the most basic level that still gives a reasonable assessment.
- Insert it with zero durations first. The Tennessee DOT CPM manual has you add the delay activities at zero duration and run the network to confirm every date is unchanged. That proves you changed nothing but the delay.
- Enter the durations and recalculate. Put in the real or agreed durations. Compare the new completion date with the old one. The difference is the time impact.
- Remove time already awarded. TDOT's manual has you take out delays already granted so you do not claim the same days twice.
One limit to keep in mind: the method assumes the work before and after the delay stays frozen, as the TDOT manual notes. If your crew resequenced around the problem, record that too.
Do not lump delays together
One fragnet per event. A lesson on AACE 52R-06 warns that bundling several delays into one fragnet hides which event caused what. That makes the claim easier to attack. A late RFI answer and a late submittal approval get separate fragnets, even if they hit the same week.
Float comes first: a worked example
Float is the slack on an activity, the days it can slip without moving the finish date. A delay on a path with float may cost the project nothing.
The same AACE lesson gives a clean example. A schedule forecasts completion on day 200. An owner-directed redesign adds a 15-working-day fragnet to a path with 4 days of total float. The first 4 days are absorbed, so the net critical impact is 11 days (15 minus 4) and completion moves to day 211. You claim 11 days, not 15.

The ABA article says the same thing in plain terms: if float absorbs the delay, completion does not change, and the delay is the variance between the unimpacted schedule and the impacted one.
For your trade, this matters when you are asked to sign a schedule. Ask who owns the float in your subcontract and the prime contract. It decides whether your late-released work area is a compensable day or an absorbed one.
Delay impact analysis with other methods
People search for "delay impact analysis" and "window analysis" in the same breath. They are different tools.
| Method | What it does | Best used |
|---|---|---|
| Time impact analysis | Models the event in the schedule and compares completion dates | While the job is running |
| Windows analysis | Compares as-planned and as-built over each update period | After the fact, on disputed jobs |
| Impacted as-planned | Same as a TIA, but against the baseline when no update exists | When updates were never issued |
Per the ABA article, the TIA suits prospective, contemporaneous work and many specifications require it. Windows analysis is observational and preferred for forensic work, but it is the most time-intensive and expensive, and it fails without reliable updates. A peer-reviewed review in MDPI Buildings adds that the time impact technique gets impractical when there are too many delay events or periodic updates are missing.
For a sub, the lesson is simple. The earlier you submit, the simpler the method you need. A TIA submitted the week of the event beats a windows analysis argued a year later.
What a trade sub needs in the file
The analysis sits on records. A delay analysis guide from an estimating firm lists the document set: baseline schedule and every update, daily reports showing manpower, equipment and weather, RFI and submittal logs, the change order register, weather observations, the contract's float and notice provisions, and meeting minutes.
The same guide notes that when a schedule update and the daily reports disagree, the field record controls. If an update shows a pour done March 15 and the daily report shows March 20, the daily report wins. That is good news for subs, because your foreman wrote that report.
A useful sub-level example from that guide: a structural engineer returns a shop drawing 12 work days late and holds up a steel crew on a zero-float path. Four of those days trace to the contractor's own anchor bolt rework, so 8 days are owner-caused. The file that proves it holds the RFI, the transmittal log, daily reports and the schedule update. Your trade will have its own version: a masonry crew waiting on a released bay, or a rough-in crew waiting on approved submittals.
Tie each day back to a record. Our guides on how foremen document delay events, submittals workflow with GCs and change order documentation cover what to capture. Meeting minutes matter too, because they show what the GC said and when.
Time first, money second
AACE 52R-06 says to quantify time before cost, and that time impacts are not necessarily a function of cost. Settle the days, then price them. A sub's extended general conditions, standby crew and remobilization come after the days are agreed.
Weather delay days
Weather is the delay every sub deals with, and the one most often rejected for thin paperwork.
What counts
Contracts usually set a baseline of normal bad weather and excuse only what exceeds it. AACE 84R-13 defines a weather day as a work day stopped or appreciably hindered by weather, planned adverse weather days as the number expected in a period, and unusually adverse weather days as actual days above plan. It also counts weather preparation days, such as securing a crane before high winds, and recovery days, such as clearing mud or flooding after a storm.
A public-owner example: the University of Tennessee system's weather delay standard (December 2018) counts a day only if precipitation over 0.1 inch, low temperatures or high sustained wind stopped work for at least half the scheduled day and critical path work was planned. Extensions apply only past the monthly baseline, for example 12 days in January and 4 in September. Your contract will have its own numbers. Read it before the season starts.

Thresholds by trade
A Florida patient tower case study shows thresholds written by trade: concrete placement delayed by rain over a quarter inch, wind gusts or cold under 40°F; steel erection stopped by sustained winds over 25 mph or lightning within 10 miles; roofing suspended for any measurable rain. Of 34 claimed weather days, 31 were approved. The three rejected failed because rain of 0.18 inches was under the 0.25-inch concrete threshold, because the delayed work was not critical, and because the foreman's note and photos were missing.
Those three failures are your checklist: meet the trade's threshold, hit the critical path, and tie the weather reading to the stoppage with a note and photos.
Document it the same day
- Log the date, hours lost, crew size and the activity stopped.
- Record the weather reading from the nearest NOAA station or the source your contract names.
- Take dated photos of the work area.
- Note any preparation or recovery work separately.
- Report it in the format the contract requires. The Tennessee standard, for instance, wants a monthly report with the next pay application.
Cold-season masonry has its own cost drivers, covered in our winter work cost factors. For crews that photograph and log conditions in the field, a software platform built for fiber and utility contractors shows how field reporting and GPS-tagged photos support weather delay documentation and claims.
A repeatable routine for your office
- Foremen log delays and weather daily, with photos.
- The PM sends written notice within the contract window.
- The PM links the event to the RFI, submittal or change order that caused it.
- The estimator or PM sizes the delay in working days, net of float.
- The GC's scheduler runs or approves the fragnet.
- You price the agreed days and attach them to a change order.
It works the same whether you are a ten-person electrical shop or a fifty-person mechanical firm. The scale changes. The discipline does not.
How Subascent fits
Subascent is job and bid management software for specialty trade subs. It includes submittal and RFI management, change order workflows, daily field reporting, labor and crew tracking through the CrewTrack mobile app, and QuickBooks sync. Those are the records a delay claim needs, kept against the job instead of in a foreman's truck. CrewTrack is free for foremen as part of the subscription.
Plans are Starter at $49 per month, Scale at $99 per month and Pro at $179 per month, with annual pricing of $490, $990 and $1,790. A PDF takeoff add-on is $99 per month. See the plans and features.

If your delay days live in texts and memory today, start with the Subascent plans and move your daily reports, RFIs and change orders into one place.
Our view
Most claims we hear about from subs do not fail on the math. They fail because nobody wrote down what happened on the day it happened.
A foreman who logs hours lost, the stopped activity and a photo before he leaves the site has done more for the claim than any scheduling expert can do later. So we built our tools around that handoff: field report, RFI, submittal and change order tied to the same job.
Subs are not GCs, and GC-built software is not built around your claim. You need your own record of what was asked, what was approved, and what it did to your crew. That is what a schedule impact analysis runs on.
Dave
FAQ
What is the difference between a schedule impact analysis and a time impact analysis?
Schedule impact analysis is the broader idea: measuring how a delay or change affects the schedule and who is responsible. A time impact analysis is the usual method, inserting the event into the last accepted CPM update and comparing completion dates.
What does an impacted schedule mean?
It is the schedule after the delay event has been inserted. Per the ABA article, it shows the event's effect on overall project completion, and it is compared with the unimpacted schedule from just before the event.
How many weather delay days can I claim?
Usually only days beyond the baseline your contract sets for that month, and only when the weather stopped critical work. Your subcontract and the prime contract name the thresholds and the data source. Send your documentation with the notice the contract requires.
When should I submit a time impact analysis?
As soon as the event occurs. AACE 52R-06 describes the TIA as a prospective method to perform while the project is ongoing. Late submissions lean on the baseline instead of a current update and are easier to dispute.
Sources
- Schedule Impact Analysis, John Hildreth
- Time Impact Analysis, Ron Winter
- Time Impact Analysis, TxDOT
- CPM Schedules How-to Manual, TDOT
- Understanding Construction Scheduling, American Bar Association
- AACE 52R-06: Prospective Time Impact Analysis
- AACE 84R-13: Planning and Accounting for Adverse Weather
- Prospective Time Impact Analysis, Constroma Learn
- Schedule Delay and Time Impact Analysis
- Weather delay standard 01 26 20, Tennessee Higher Education
- Florida patient tower weather days case study
- Construction Delay Analysis Techniques, MDPI Buildings
- Features for fiber and utility contractors