A good daily report answers six questions: who was on site, what they did, what was delivered, what slowed them down, what was inspected, and what the office needs to do next. If your foreman's report covers those six, it will hold up in a back-charge dispute, a change order request or a payment fight. This page gives you the full checklist, the photo habits that go with it, and examples you can copy for masonry, electrical, plumbing and HVAC crews.
TL;DR
- File one report per crew per workday, no later than the next working day, per FASA's project documentation guidance.
- Log the date, start and stop times, named crew, weather, work by area, materials, equipment, safety, visitors and inspections.
- Write delays and extra work as facts: what happened, who caused it, when, and how many crew hours it cost.
- Name photos by date, location, subject, status and sequence so anyone can find them in seconds.
- Have the office review reports every week. A report nobody reads does not protect you.
Table of Contents
- Why the daily report matters to a sub
- The daily report checklist
- What a usable entry looks like
- Daily report examples by trade
- Field photos: what to shoot and how to name them
- Punch list photos: issue, location, correction
- Making the report a habit
- Perspective
- Put the checklist into your workflow
- FAQ
- Sources
Why the daily report matters to a sub
The general contractor keeps a superintendent's log. You keep yours. When a GC claims you were late, or you claim another trade blocked your crew, the side with the dated record usually wins the conversation.
The American Subcontractors Association's project documentation material calls the daily report the key link between the field and the home office. It says reports should be made daily, be complete, reach the office, and be reviewed by management. FASA's guide adds that contemporaneous, consistent records are the most reliable kind. That means written on the day, in the same format, every day.
Some public jobs make it a contract requirement. One Delaware public-project specification, Section 013226 on subcontractor daily reports, asks for work in progress by area and operation, manpower, extra work, materials received, each worker's trade and hours, and a daily inspection checklist. It wants the report and any authorized extra-work report in by 9:00 a.m. the next workday. Your contract may say something different, so read the reporting clause before the job starts.
The daily report checklist
Use this as your base form. Every line should take a foreman seconds to fill in, not minutes.
Job and time
- Job name, job number and address
- Date and report number
- Foreman's name
- Start time and stop time, including any after-hours work
FASA's list starts with date, start and stop times, and the NAHB daily report form adds project and job number, superintendent and a signature line.
Crew and hours
- Every crew member by name, with trade or classification and hours worked
- Apprentices, laborers and any temporary help listed separately
- Standby time, when people were on site but could not work
The ASA material names labor hours and standby time as essential content. Standby is the line most foremen skip, and it is the one that supports a delay claim. If you need a clean way to get hours out of the field, see how foremen track crew hours on the job site.
Weather
- Conditions, temperature, wind and precipitation, morning and afternoon if they changed
- Whether weather stopped or slowed any operation
Weather is on every form we looked at, including the NAHB form, which also asks for temperature and wind. For masonry, concrete and roofing, it often decides whether the day counts as a lost day.
Work performed
- Work completed, by area, floor or elevation
- Work in progress and percent complete where you track it
- Quantities: linear feet, square feet, blocks laid, fixtures set, devices pulled
- Tomorrow's plan
The quantities are what separate a report from a diary. "Worked on 2nd floor" tells nobody anything. For production tracking, our guide on what a daily production report is for subcontractors shows how to turn these numbers into productivity rates.
Materials and equipment
- Materials delivered, with quantities and who signed for them
- Materials used
- Materials needed and when
- Equipment on site: lifts, scaffolding, saws, mixers, cranes
Deliveries are where a lot of money disappears, either as shortages nobody caught or as damage nobody photographed. A freight and receiving checklist walks through what to check when product arrives, and the same habit belongs on your report. For masonry crews, we cover the routine in how foremen document material deliveries in masonry.
Delays, extra work and communications
- Delay events: cause, who was responsible, start and end times, crew affected, impact
- Extra or out-of-scope work, who directed it, and who approved it
- Field-generated RFIs
- Instructions received from the GC or another trade
FASA lists field-generated RFIs, special visitors and third-party inspections as items to record when they apply. Delay entries need the most care. We break them down in how foremen document delay events on the job site.
Safety, inspections and visitors
- Toolbox talk topic and attendance
- Incidents, near misses and hazards reported
- Inspections held and the result
- Visitors: GC, owner's rep, inspector, supplier
If your foremen are responsible for the site safety plan, this foreman safety checklist covers what belongs in it. The Delaware specification mentioned above also requires a daily inspection checklist as part of the report.
Photos and sign-off
- Photo count and file range (for example, photos 12 to 19)
- Foreman's signature or initials
- Office review initials and date
What a usable entry looks like
The difference is detail. Compare two entries for the same day.
Weak: "Worked on east wall. Short on block. GC late."
Usable: "Crew of 4 plus 1 laborer laid 620 CMU on east wall, grid C to F, level 1, up to 8 ft lift. Stopped at 1:15 p.m.: 8-inch block delivery short by 180 units, shown on delivery ticket 4471, photo 6. Called the GC superintendent at 1:20 p.m.; he confirmed the supplier would re-ship. Crew moved to cleanup and mortar prep for 2.5 hours. Re-ship expected tomorrow at 7 a.m."
The second entry gives the office quantities, a time, a name, a cause and a lost-hours number. That is what turns a field note into backup for a back-charge defense or a delay notice.

Daily report examples by trade
The fields stay the same. The quantities and inspections change with the trade. Here is what to add.
| Trade | Quantities to log | Trade-specific items |
|---|---|---|
| Masonry | Block or brick laid by elevation, lifts, scaffold height | Mortar batches, grout pours, rebar and ties inspected, cold-weather protection |
| Electrical | Conduit feet, wire pulled, devices and fixtures set | Panel or circuit status, rough-in inspection result, lockout and tagout notes |
| Plumbing | Pipe feet by system, fixtures set | Pressure test results, rough-in inspection, hangers and sleeves by floor |
| HVAC/mechanical | Duct feet, units set, line sets run | Crane or lift use, curb and flashing status, startup and balancing steps |
| Roofing | Squares installed, flashing linear feet | Deck conditions, stored materials, existing damage, substrate repairs |
| Drywall and framing | Sheets hung, studs framed, areas taped | Area turnover, backing and blocking inspected, hold-ups from other trades |
For roofing, Professional Roofing magazine says a quality-assurance daily report should note site and roof conditions, stored materials, pre-existing or new damage, substrate repairs, installation and flashing details, weather, crew size, foreman and visitors, with photographs. It recommends the report reach the roofing contractor no later than the start of the next day, and it points to ASTM D7186 sample forms for damage, deliveries, daily construction and progress.
For masonry crews, we have a full set of formats in masonry sub daily production report examples.
Field photos: what to shoot and how to name them
Photos back up every line of the report. They also fill in the gaps a foreman does not have time to write.
What to shoot
ASA recommends photographing at least weekly, plus any changes, completed work or milestones, and impacts caused by the general contractor or other trades. In practice, that means:
- Start of work in each area, before you touch it
- Existing conditions that are not yours: damaged substrate, out-of-plumb walls, missing blocking
- Work in progress at hidden stages: rebar before the pour, rough-in before the drywall closes it
- Completed work at turnover
- Anything that blocks your crew, with the blocker in frame
Metadata that matters
The same ASA document advises using a date-stamped camera, shooting recurring progress photos from the same spot and direction, and including a measuring device or object for scale. Add three practical habits:
- Keep the date and time on the phone correct, since the file stamps will be what you rely on later.
- Do not edit or crop the original. Work from copies.
- Write the area or grid line in the report entry, not only in the photo.
A naming convention that works
Pick one pattern and make every foreman use it. A simple one is:
Date_Job_Location_Subject_Status_Sequence
Example: 2026-11-13_Hillcrest_L2-GridC_EastWall_Before_01
Why this order:
- Year-month-day sorts correctly in any folder.
- The job comes next so photos never get mixed between projects.
- Location and subject mean a PM can search "GridC" or "Rebar" and find the right shot.
- Status (Before, During, After, Damage, Punch) tells the reader what the photo proves.
- A two-digit sequence keeps files in order.
Keep names short, avoid spaces and special characters, and write the convention on one card the foreman keeps in the truck. Our field photo documentation workflow shows how to set this up for a whole crew.
Punch list photos: issue, location, correction
Punch items drag on because nobody can tell which item is which. Use three photos per item:
- The issue. Close enough to see the defect, with a tape or marker for scale.
- The location. A wider shot showing the room, wall or grid line, so the item is findable.
- The correction. Taken from the same spot and angle as the first photo.
Name them with the same convention, using Punch and then Before or After in the status slot, and add the punch item number from the GC's list. Log the item in that day's report with the date closed. When the GC signs off, you have a before and after pair tied to a date and a name. That pair settles most "you never fixed that" arguments.
Making the report a habit
The checklist fails when it is too long or arrives too late. Four rules help.
Keep it to one screen or one page. Foremen finish what is short. Put the fields you need on the form and leave out the rest.
Fill it in at the same time every day. Last 15 minutes of the shift, before the crew leaves. Not at home that night.
Use a default for everything that does not change. Job name, address and foreman should already be on the form. Pick lists for trade, area and delay cause beat typing.
Review weekly. The ASA says management should regularly review reports. A PM scanning a week of reports can catch a short delivery, a missing inspection or a crew running 20 percent behind plan while there is still time to act. Common problems on the foreman side are covered in foreman job site communication mistakes to fix.

Where do the hours go? Once the report is in, timecards should match it. If they do not, you have found a gap. Our guide to timecard approvals for trade subcontractors covers that handoff.
Perspective
Paper reports and photo folders on a foreman's phone work until the job gets busy. Then the report gets written from memory on Friday, the photos have names like IMG_4471, and the PM is chasing hours for payroll.
We built Subascent for specialty trade subs, so the daily report sits next to the things it feeds: labor and crew tracking, the job budget, change orders and invoicing. Foremen use the free CrewTrack mobile app that comes with the subscription, so the report starts in the field, not in the office.
Our view is simple. A daily report should take a foreman a few minutes, and the office should get something it can use the same day. That is how you find out which jobs are making money before they close.
Dave
Put the checklist into your workflow
If you want the checklist built into how your crews already work, Subascent includes daily field reporting, labor and crew tracking, change order workflows and QuickBooks sync for specialty trade subs. Foremen get the free CrewTrack mobile app as part of the subscription. Plans are published at Starter $49 per month, Scale $99 per month and Pro $179 per month, or $490, $990 and $1,790 per year. PDF takeoff is a paid add-on. See the plans and features or start from the Subascent home page.

FAQ
What should a daily report checklist include?
At minimum: date, start and stop times, crew members by name, weather, work performed by area, materials, equipment, safety issues and anything affecting progress. Add visitors, inspections and field-generated RFIs when they happen, as FASA's project documentation guide recommends. Include quantities so the report can feed productivity tracking.
Who writes the daily report, and when?
The foreman writes it for each crew. FASA's guidance is to make it on the workday or no later than the next working day. Some contracts set a hard deadline, such as 9:00 a.m. the next workday in the Delaware specification, so check yours.
How many photos should go with each report?
Enough to prove the key facts of the day: start conditions, hidden work before it is covered, completed work, deliveries, and anything blocking the crew. ASA recommends photographing at least weekly, plus changes, milestones and impacts from the GC or other trades. On active days, most reports need several photos, not dozens.
How do I name field photos so I can find them later?
Use a pattern like date, job, location, subject, status and sequence, with the date written year-month-day so files sort in order. Example: 2026-11-13_Hillcrest_L2-GridC_EastWall_Before_01. Apply it the same way on every job.
Do daily reports help with change orders?
Yes. A report that records who directed extra work, when, and how many hours it took gives you the backup to price and defend the change order. The Delaware specification even requires a separate authorized extra-work report alongside the daily report.
Sources
- Project Documentation, FASA
- Section 013226 Subcontractor Daily Reports, State of Delaware
- Basic Construction Management daily report form, NAHB
- Project Documentation, American Subcontractors Association
- Tech Today, Professional Roofing