Subcontractor invoice terms come down to three questions: when is the invoice due, what has to happen before it is paid, and how much is held back. "Net 30" answers the first. A pay-when-paid or pay-if-paid clause answers the second. Retainage answers the third. If your subcontract has Net 30 on the invoice but a condition buried in the contract, the contract wins. Trade firms that track all three on every job know their real cash gap before they sign. We built Subascent for that, with invoicing and financials in the same place as your bids and jobs.
TL;DR
- Net 30 means payment is due 30 days after the invoice date. Pay-when-paid and pay-if-paid clauses can push the real payment date much later.
- Pay-when-paid ties timing to the GC getting paid. Pay-if-paid makes the owner's payment a condition of you being paid at all. Enforceability depends on the state.
- Retainage of 5 to 10% is common on progress billing. Check the percentage, the step-down and the release trigger before you sign.
- Most rejected invoices are missing paperwork: the subcontract number, approved change orders, the schedule of values and the prior lien waiver.
- Write payment terms into the subcontract, not just onto the invoice.
Table of Contents
- What invoice terms mean on a trade job
- Net 30 is not always Net 30
- Pay-when-paid vs. pay-if-paid
- Retainage: the term that holds your margin
- State prompt payment rules
- What goes on the invoice
- When the invoice is late
- Perspective
- Put your terms and billing in one place
- FAQ
- Sources
What invoice terms mean on a trade job
Payment terms tell the customer when and how to pay. On a construction job, that customer is usually a general contractor, and the terms live in two places: the subcontract and the invoice (called a pay application when you bill progress). If they disagree, the signed subcontract controls. OnPay notes that no federal law sets one payment timeline for all businesses, and that the terms in a signed contract are legally binding.
The common terms:
| Term | What it means | Where it fits |
|---|---|---|
| Due on receipt | Payment is due as soon as the invoice is issued or work is delivered. Stripe says it suits small one-time jobs and new customers. | New or high-risk customers, small service calls |
| Net 15 | Due 15 days after the invoice date | Short jobs, tight cash flow |
| Net 30 | Due 30 calendar days after the invoice date. | Most commercial work |
| Net 45 / Net 60 | Due 45 or 60 days after the invoice date | Customers that insist on long terms |
| 2/10 Net 30 | 2% discount if paid within 10 days, otherwise full amount in 30 | Speeding up slow payers |
Construction Cost Accounting lists Net 30 as the most common commercial term and Net 15 for smaller or short jobs. For a drywall or painting sub billing a GC monthly, Net 30 is the usual ask. The trouble starts with what is attached to it.
Net 30 is not always Net 30
True Net 30 is unconditional. You invoice, the clock starts, and nothing upstream has to happen first. CentSight argues that this is rare below the GC tier and that most subs sign Net 30 with a condition attached.
Here is the math it gives. Under true Net 30 with a monthly pay-app cycle, your cash is out roughly 45 to 60 days: 30 days of work, then 30 days waiting. Add a pay-when-paid clause and that exposure can stretch to 75 to 90 days. On a $500,000 job billed monthly, that is roughly $125,000 of unfinanced work at the peak. For a plumbing or electrical sub carrying payroll and material bills every week, that gap is the whole problem.

Pay-when-paid vs. pay-if-paid
These two clauses sound alike and act very differently.
- Pay-when-paid: the GC still owes you. Only the timing is tied to when the GC receives payment from the owner. AIA's contract guidance describes it this way.
- Pay-if-paid: the GC's receipt of owner payment is a condition of its obligation to pay you. If the owner never pays, the GC may say it never owed you.
How courts treat them depends on the state. Kegler Brown's 2025 50-state survey reports that for more than 30 years most state courts have held a GC cannot withhold payment indefinitely under a pay-when-paid clause. It must pay within a reasonable time after satisfactory work. Pay-if-paid clauses are enforced only where the contract clearly says so, and a growing number of states have declared them void. A few jurisdictions treat the two clauses as having the same effect, so where the project sits matters. For example, the NECA handbook states that pay-if-paid provisions are unenforceable in California.
The practical read: get a lawyer who knows the project's state to review any contingent payment clause before you sign. A short review costs far less than a stalled $125,000 exposure. For a deeper look at how contingent payment language plays out in contracts, see this piece on contingent payment clauses and subcontractor payment rights.
A redline many GCs accept
If you cannot remove pay-when-paid, cap it. CentSight suggests language that pays within seven days of the GC's receipt of owner funds, but no later than sixty days after your invoice. It reports that most GCs accept this because it only limits the tail. Have your attorney adapt it to your contract and state.
Retainage: the term that holds your margin
Retainage is a percentage withheld from each progress payment to secure completion. AIA explains that it may be released as the project moves forward or held until completion, and that your subcontract should mirror the retainage amount and release timing in the owner-GC agreement. Typical retainage runs 5 to 10%.
On a $400,000 masonry contract at 10%, that is $40,000 sitting with someone else, often your entire profit and then some. Before you sign, run through the checks from SMACNA's payment and retainage bulletin:
- Is the retainage percentage set artificially high?
- Is yours higher than the GC's own?
- Does it step down after substantial completion?
- Does the subcontract have pay-when-paid language?
- Are stored materials payable on notification and verification?
- Is your release tied to your own work's acceptance, or to the whole project's completion?
Item 6 catches the most people. A framing or concrete sub finishes early and then waits months for a retainage release tied to a project it no longer touches. Retainage laws also vary by state, with some capping the percentage or setting release deadlines.
On the AIA forms, the G702/G703 application tracks retainage line by line against the schedule of values. Our guides on the AIA payment application and masonry retainage release walk through the mechanics, and the QuickBooks retainage setup shows how to keep it straight in your books.
State prompt payment rules
Many states set outside limits on payment timing, and they differ. ReviewMyContract cites California at 7 days after the prime contractor receives owner funds and Texas at 35 days. For Construction Pros reports that New York's amendments, for contracts over $150,000 entered on or after November 17, 2023, cap owner retainage at 5% and require payment to lower-tier subs within 60 days. It also reports that Virginia requires payment to subs on public projects within 60 days of invoice receipt, whether or not the contractor has been paid.
These rules change. Check your state's current statute, or ask your attorney, before you rely on a number.
What goes on the invoice
ClearReceivables says missing documentation is the top reason contractor invoices are rejected or delayed. The invoice has to match the GC's project records: scope, contract amount, change orders and percent complete. Include:
- The subcontract or PO number
- Work completed this billing period
- Approved change orders with signed authorization
- A lien waiver for the previous payment
- Clearly stated payment terms
- A schedule of values showing percent complete by line item, for progress billing
Deltek adds that backup commonly includes daily logs, timesheets, material receipts and certified payroll where it applies.
Timing matters too. ClearReceivables recommends invoicing within 24 hours of a billing milestone. Some GCs enforce cutoffs hard: one GC's published policy requires invoices within 14 days of work completion and treats invoices more than 30 days late as ineligible. Read the GC's cutoff in your subcontract and bill ahead of it. Our progress claims guide covers the monthly rhythm, and the invoice approval workflow covers how to move paper through your own office.
When the invoice is late
Start with the contract. Under ConsensusDocs 750, as SMACNA describes it, the contractor must pay within a reasonable time even if the owner has not paid, unless your fault caused the non-payment. You may stop work if a progress payment is not received within seven days after it is due and you have given seven days' written notice. You may terminate if work has been stopped for 30 calendar days. Your contract may differ, so read it.
Preliminary notice also matters. The NECA handbook notes that in most cases a notice at the start of work is a prerequisite to enforcing mechanics liens, stop payment notices and payment bonds, and the deadlines are strict. Send it on day one, not when you are already late. Talk to a construction attorney before you stop work or file a lien.

SMACNA also advises checking whether a payment and performance bond is in place and whether financing is committed before you sign. For routine follow-up, our 30-minute AR routine keeps invoices from aging past 90 days, and the cash flow warning signs post helps you spot trouble early.
Perspective
Most subs we talk to about invoice terms focus on the number: Net 30, Net 45. The number is the least important part. The conditions around it decide when you eat.
Our view is that you should know your cash gap before you sign, not after the second pay app is late. That means the invoice date, the pay-when-paid language, the retainage percentage and the release trigger, all on one page, for every job.
That is why Subascent puts invoicing and financials next to your bids, change orders and field reports. Billing from the same record you priced and tracked means the schedule of values, approved changes and daily reports are already there when you build the pay app. Profit analytics show budget against actual while the job is still open, and QuickBooks sync keeps the books matched.
Run the terms through that lens on your next bid.
Dave
Put your terms and billing in one place
Subascent is job and bid management software for specialty trade subs, including electrical, plumbing, HVAC, masonry, concrete, drywall and roofing. Starter is $49 per month or $490 per year, Scale is $99 per month or $990 per year, and Pro is $179 per month or $1,790 per year. See the plans on the pricing page or look at invoicing and financials.

FAQ
What does "Net 30" mean on a subcontractor invoice?
It means full payment is due within 30 calendar days of the invoice date. Check the subcontract too, because a pay-when-paid or pay-if-paid clause can make the real payment date later than day 30.
What is the difference between pay-when-paid and pay-if-paid?
Pay-when-paid delays payment until the GC is paid but still obligates the GC to pay within a reasonable time. Pay-if-paid makes owner payment a condition of the GC's duty to pay you. Enforceability varies by state, so have an attorney review the clause.
How much retainage is normal?
Retainage of 5 to 10% of each progress payment is common. Some states cap it, and your subcontract should match the owner-GC retainage terms and release timing.
Should I put payment terms on the invoice or in the contract?
Both, and they must agree. The signed subcontract controls, so negotiate there. The invoice should restate the terms clearly so the GC's office cannot miss them.
Sources
- OnPay: Common Payment Terms for Contractors
- Stripe: What are 30 days payment terms?
- Xero: Invoice payment terms
- Construction Cost Accounting: Invoice Payment Terms Explained
- CentSight: Subcontractor Payment Terms
- AIA: How to Improve the Subcontractor Payment Process
- Kegler Brown: Contingent Payment Clauses in the 50 States 2025
- NECA Subcontractor Contract & Collections Handbook
- SMACNA: Payment and Retainage bulletin
- ReviewMyContract: Payment Terms and Late Fees
- For Construction Pros: Recent legislative updates to prompt payment laws
- ClearReceivables: Contractor Collections
- Deltek: Construction Invoicing 101
- Toland Construction: Invoice Cut Offs & Deadlines Policy